The proposed project would resurface about 2.94 miles of US-73, starting at 7th Street,
just north of the southern corporate limits of Falls City, and extending to approximately one mile
north of the northern corporate limits of Falls City.
The project would consist of milling and resurfacing the existing roadway and shoulders.
The project would also include concrete repairs, curb ramps, grading and removing guardrail.
The four-lane section from 7th Street to 19th Street would be reduced to three lanes, including a
northbound, southbound, and a center two-way left-turn lane. The three lanes would be
reconstructed with full depth concrete pavement.
Personnel from the Department of Roads will be available to answer questions, receive
comments, and discuss any aspect of the proposed highway improvement project. Information
regarding the project will be available after the meeting on the NDOR website at
www.roads.nebraska.gov/projects/ by clicking on the “In Falls City and North” link.
Contact:
Tom Goodbarn, District 1 Engineer, Lincoln, (402) 471-0850